Recent Projects

Hanger Road – Airport Job

Installation 1500’ of 8” plastic natural gas mainline along Hanger Rd within the Pittsburgh International Airport. Replacement of steel valves and installation of a regulator station were also included within the scope of work. Location: Hanger Road For: Peoples Natural Gas

Equitable Gas Company M-77 Jones Farm and Duquesne Works Pig Launchers

Install and perform all excavation for the pig launchers and receivers at the Jones Farm and Duquesne Works locations in conjunction with Power Piping Company. For: Equitable Gas Company  

Rural Valley ROW Project

Installation of over 9600’ of 8” plastic natural gas mainline through Equitable Gas ROW. This project called involved a variety of pipe laying techniques  including the use of a trencher and a 500’ directional drill. For: Equitable Gas Company  

US Steel Building Project

Installation of 1600’ of 12” and 400’ of 4” plastic natural gas main in Downtown Pittsburgh in order to provide service to the US Steel Tower. This project in the heart of Pittsburgh also included surface restoration of necessary roadways and sidewalks. For: Peoples Natural Gas

West Liberty Avenue Project

This was a multi-phase, natural gas facilities replacement and pressure up-rate project for Columbia Gas of Pennsylvania. The four phases, when completed, consisted of over 10,000’ of plastic natural gas mainline, sizes ranging from 2” to 8”, 1600’ of 10” steel mainline and multiple regulator stations. This project also called for the complete replacement of… View Article